3025 BOILER STEAM TESTED
April 5, 2011, Wayne Hebert Looks Over His Work
3025 has slid in and out of the shop several times in the last month. The final step in making an alteration of a boiler under FRA (Federal Railroad Administration) jurisdiction is a steam test of the boiler to operating pressure. We did this for ourselves in March to be sure that we wouldn't be wasting the FRA's time coming up to witness the test. Once certain that all was in readiness, we scheduled the inspection.
April 5th wasn't a good day weather wise, but for the No.3025 project, it was excellent. The FRA was pleased with the test, so now we are clear to apply the insulation and boiler jacket.